powered help
header-left header-center header-right
File #: 190285    Version: 0
Type: Resolution Status: Passed
File created: 5/29/2019 In control: COMMON COUNCIL
On agenda: Final action: 6/18/2019
Effective date:    
Title: Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $174,000 for a total estimated cost of these projects being $4,810,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Number
190285

Version
ORIGINAL

Sponsor
THE CHAIR

Title
Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $174,000 for a total estimated cost of these projects being $4,810,000.

Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $174,000 with the total cost estimated to be $4,810,000.

Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

3rd Aldermanic District

N. Arlington Pl. - N. Warren Ave. to 130’ +/- north of N. Warren Ave. (SM495190016) Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $10,000). The total estimated cost of this project including the requested amount is $15,000. This project is anticipated to be completed during the 2019 construction season.

8th Aldermanic District

S. 33rd St. - W. Rogers St. to 400’ +/- south of W. Becher St. (SM494190014) Relaying sanitary sewer. (Infiltration/Inflow Reduction Fund -- $12,000). The total estimated cost of this project including the requested amount is $262,000. This project is anticipated to be completed during the 2020 construction season.

8th and 12th District

S. 20th St. - W. Cleveland Ave. to a point 730’ +/- south of W. Cleveland Ave. (SM494190020) Relaying sanitary sewer. (Infiltration/Inflow Reduction Fund -- $12,000). The total estimated cost of this project including the requested amount is $197,000. This project is anticipated to be completed during the 2020 construction season.

S. 20th St. - W. Windla...