Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $4,597,000 for a total estimated cost of these projects being $5,450,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. NFR 12 Sub.pdf
Number
190149
Version
Substitute 1
Reference
180759
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $4,597,000 for a total estimated cost of these projects being $5,450,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $4,597,000. The total estimated cost of these projects is $5,450,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

2nd Aldermanic District

N. 68th St. - W. Congress St. to W. Ruby Ave. (SM494180025) File Number 180759: Relaying sanitary sewer. (Infiltration/Inflow Reduction Fund -- $184,000.) The total estimated cost of this project including the requested amount is $196,000. This project is anticipated to be completed during the 2019 construction season.

3rd Aldermanic District

N. Cramer - E. Bradford Ave. to E. Park Pl. (SM495180064) File Number 180872: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $161,000). The total estimated cost of this project including the requested amount is $173,000. This project is anticipated to be completed during the 2019 construction season.

E. Newport -- N. Summit Ave. to N. Hackett Ave. (SM495180051) File Number 180399: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $47,000). The total estimated cost of this project including the requested amount is $57,000. This project is anticipated to be completed dur...