powered help
header-left header-center header-right
File #: 190147    Version:
Type: Resolution Status: Passed
File created: 5/7/2019 In control: COMMON COUNCIL
On agenda: Final action: 5/29/2019
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $215,700 for a total estimated cost of $230,600.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Attachments: 1. Signed Letter.pdf, 2. Signed AD.pdf, 3. Official Notice.pdf, 4. Proof of Publication
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
6/7/20192 MAYOR SIGNED   Action details Meeting details Not available
5/29/20192 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Video Video
5/15/20190 PUBLIC WORKS COMMITTEE AMENDED

Minutes note: Appearing : Mary Dziewiontkoski 8th Aldermanic District W. Mineral St. – S. 24th St. to S. 25th St. (ST211190111) Install traffic calming speed hump(s). Dist. Ald. Support project there were no residents to testify when called. Ald. Borkowski moved approval 5-0 W. Mineral St. – S. 25th St. to S. 26th St. (ST211180275) Install traffic calming speed hump(s). Dist. Ald. support project there were no residents to testify when called. Ald. Borkowski moved approval 5-0 W. Rogers St. – S. 23rd St. to S. 24th St. (ST211180268) Install traffic calming speed hump(s). there were no residents to testify when called Ald. Borkowski moved approval 5-0 S. 25th St. – W. Mineral St. to W. National Ave. (ST211180271) Install traffic calming speed hump(s). Dist Ald. Support the project there were no residents to testify when called Ald. Borkowski moved approval 5-0 13th Aldermanic District S. 22nd Pl. – W. Mallory Ave. to W. Clayton Crest Ave. (ST211060118) Asphalt pavement resurfacing, replace curb and gutter and driveway approaches where necessary, install concrete walk, sodding ( 10’ width of tree border area), and grading. Dist Alderman support project except sidewalk project Ald. Johnson moved approval based on Dist Ald. support 5-0 S. 25th St. – W. Holt Ave. to W. Ohio Ave. (ST211190113) Install traffic calming speed hump(s). Ald. Johnson moved approval 5-0 15th Aldermanic District N. 25th St. – W. Center St. to W. Hadley St. (ST211190107) Install traffic calming speed hump(s). Ald. Kovac moved approval 5-0
   Action details Meeting details Video Video
5/15/20191 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass5:0 Action details Meeting details Not available
5/7/20190 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

190147

Version

SUBSTITUTE 2

Reference

040689

Sponsor

THE CHAIR

Title

Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $215,700 for a total estimated cost of $230,600.

Analysis

This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held.  The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.  The City cost of these projects approved by this resolution is estimated to be $215,700.  The total estimated cost of these projects is $230,600.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

 

8th Aldermanic District

 

W. Mineral St. - S. 24th St. to S. 25th St. (ST211190111) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $3,100; Nonassessable Reconstruction Paving Fund -- $4,100) The total estimated cost for this project including the requested amount is $7,200.  This project is anticipated to be completed during the 2019 construction season.

 

W. Mineral St. - S. 25th St. to S. 26th St. (ST211180275) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $2,700; Nonassessable Reconstruction Paving Fund -- $4,300) The total estimated cost for this project including the requested amount is $7,000.  This project is anticipated to be completed during the 2019 construction season.

 

W. Rogers St. - S. 23rd St. to S. 24th St. (ST211180268) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $3,700; Nonassessable Reconstruction Paving Fund -- $3,100) The total estimated cost for this project including the requested amount is $6,800.  This project is anticipated to be completed during the 2019 construction season.

 

 

S. 25th St. - W. Mineral St. to W. National Ave. (ST211180271) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $3,100; Nonassessable Reconstruction Paving Fund -- $4,500) The total estimated cost for this project including the requested amount is $7,600.  This project is anticipated to be completed during the 2019 construction season.

 

13th Aldermanic District

 

S. 22nd Pl. - W. Mallory Ave. to W. Clayton Crest Ave. (ST211060118)  File Number 040689 Asphalt pavement resurfacing, replace all curb and gutter and driveway approaches where necessary, (NO NEW SIDEWALK)  sodding ( 10’ width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $9,100; Nonassessable Reconstruction Paving Fund -- $160,000). The total estimated cost for this project including the requested amount is $184,000.  This project is anticipated to be completed during the 2019 construction season. 

 

S. 25th St. - W. Holt Ave. to W. Ohio Ave. (ST211190113) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $8,000; Nonassessable Reconstruction Paving Fund -- $2,000) The total estimated cost for this project including the requested amount is $10,000.  This project is anticipated to be completed during the 2019 construction season.

 

15th Aldermanic District

 

N. 25th St. - W. Center St. to W Hadley St. (ST211190107)  Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $6,000; Nonassessable Reconstruction Paving Fund -- $2,000) The total estimated cost for this project including the requested amount is $8,000.  This project is anticipated to be completed during the 2019 construction season.

 

; and

 

Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and

 

Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works’ Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it

 

Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it

 

Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That projects  W. Mineral St. (ST211190111); W. Mineral St. (ST211180275); W. Rogers St. (ST211180268); S. 25th St.(ST211180271); S. 22nd Pl. (ST211060118); S. 25th St. (ST211190113); N. 25th St.(ST211190113). will be billed after January 1, 2021, but not before 12 months after the project contract has been completed;

 

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/dl

Afr 12