Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,749,000 for a total estimated cost of these projects being $12,676,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

Number

161153

Version

Substitute 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,749,000 for a total estimated cost of these projects being $12,676,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $1,749,000 with the total cost estimated to be $12,676,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

1st, 4th, 7th and 12th Aldermanic Districts

 

Bioretention Maintenance Contract - North various locations (SM499160124):  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $5,000).  The total estimated cost for this project including the requested amount is $90,000.  This project is anticipated to be completed during the 2017 construction season.

 

2nd, 7th, and 10th Aldermanic District

 

North 60th Street Bioswales:  N. 60th St. - W. Burleigh St. to W. Capitol Dr. (SM499160119):  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $10,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2017 construction season.

 

2nd and 9th Aldermanic District

 

West Mill Road Bioswales:  W. Mill Rd. - N. 43rd St. to N. 91st St. (SM499160121):  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $10,000).  The total estimated cost for this project including the requested amount is $400,000.  This project is anticipated to be completed during the 2017 construction season.

 

4th Aldermanic District

 

N. Jackson St. - E. Buffalo St. to E. St. Paul Ave. (SM495160089):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $64,000.  This project is anticipated to be completed during the 2017 construction season.

 

5th Aldermanic District

 

Hartung Quarry Floating Islands:  W. Concordia Ave. at Menomonee River Pkwy. (SM499160110):  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $10,000).  The total estimated cost for this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2017 construction season.

 

8th Aldermanic District

 

W. Branting Ln. - S. 33rd St. to 175 feet east of S. 33rd St. (SM495160088):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $54,000.  This project is anticipated to be completed during the 2017 construction season.

 

W. Pierce St. - S. 37th St. to S. 39th St. (SM495160091):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $154,000.  This project is anticipated to be completed during the 2018 construction season.

 

2017 Detention Pond Dredging City of Milwaukee Lincoln Yards (Tow Lot) - 3801 West Lincoln Avenue (SM499160126):  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $5,000).  The total estimated cost for this project including the requested amount is $260,000.  This project is anticipated to be completed during the 2017 construction season.

 

9th Aldermanic District

 

West Brown Deer Road Bioswales:  W. Brown Deer Rd. - N. 68th St. to N. 124th St. (SM499160123):  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $10,000).  The total estimated cost for this project including the requested amount is $400,000.  This project is anticipated to be completed during the 2017 construction season.

 

West Good Hope Road Bioswales:  W. Good Hope Rd. - N. 43rd St. to N. 91st St. (SM499160122):  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $10,000).  The total estimated cost for this project including the requested amount is $400,000.  This project is anticipated to be completed during the 2017 construction season.

 

11th Aldermanic District

 

W. Ohio Ave. - S. 35th St. to S. 39th St. (SM495160090):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $274,000.  This project is anticipated to be completed during the 2018 construction season.

 

South 76th Street Bioswales:  S. 76th St. - Honey Creek Pkwy. To W. Waterford Ave. (SM499160120):  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $10,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2017 construction season.

 

11th and 13th Aldermanic Districts

 

Bioretention Maintenance Contract - South various locations (SM499160125):  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $5,000).  The total estimated cost for this project including the requested amount is $115,000.  This project is anticipated to be completed during the 2017 construction season.

 

City Wide

 

Administration and maintenance of the Pavement Management Administration System (PMA) (ST30581901).  (Nonassessable Reconstruction Paving Fund -- $50,000).  Administration and maintenance of the PMA system utilizing Stantec Road Matrix software.  The City Comptroller is authorized to transfer $50,000 from the Major Street Improvement parent account 0333-ST320160000, to an expenditure account previously created within the Capital Improvement Fund-Grant and Aid Projects (ST30581901) for the PMA.  The total estimated cost for this project is $135,000.  This project is anticipated to be completed in 2017.

 

Water Alterations - Developer Funded (WT430170300):  Water main alteration.  (Nonassessable Water Fund Budget Line 6410 -- $75,000).  The total estimated cost for this project is $75,000.  This project is anticipated to be completed during the 2017 construction season.

 

Work by Milwaukee Water Works Prior to Paving (WT410170730):  Water main alteration.  (Nonassessable Water Fund Budget Line 6410 -- $15,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2017 construction season.

 

Work done by Contractor - Paving (WT410170750):  Water main alteration.  (Nonassessable Water Fund Budget Line 6410 -- $15,000).  The total estimated cost for this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2017 construction season.

 

Work done by Contractor - Sewer Alterations (WT410170770):  Water main alteration.  (Nonassessable Water Fund Budget Line 6410 -- $15,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2017 construction season.

 

Suburban Plan Reviews (WT440170800):  Plan review.  (Nonassessable Water Fund Budget Line 6410 -- $50,000).  The total estimated cost for this project is $50,000.  This project is anticipated to be completed during the 2017 construction season.

 

Post Guarantee Work on Water Mains (WT410170850):  Inspection.  (Nonassessable Water Fund Budget Line 5010 -- $5,000).  The total estimated cost for this project is $5,000.  This project is anticipated to be completed during the 2017 construction season.

 

Material Inspection at Various Locations (WT410170880):  Inspection.  (Nonassessable Water Fund Budget Line 6410 -- $15,000).  The total estimated cost for this project is $15,000.  This project is anticipated to be completed during the 2017 construction season.

 

2017 Indirect Account (SM495170001):  (Nonassessable Sewer Maintenance Relay Fund -- $800,000).  The total estimated cost for this project is $800,000.  This project is antipated to be completed during the 2017 construction season.

 

2017 Outfall Maintenance and Repair - Various Locations (SM499160127):  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $5,000).  The total estimated cost for this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2017 construction season.

 

2017 Paving Coordination (SM495170002):  (Nonassessable Sewer Maintenance Relay Fund -- $300,000).  The total estimated cost for this project is $300,000.  This project is anticipated to be completed during the 2017 construction season.

 

2017 Sewer Exam Requests (SM495170003):  (Nonassessable Sewer Maintenance Relay Fund -- $100,000).  The total estimated cost for this project is $100,000.  This project is anticipated to be completed during the 2017 construction season.

 

2017 Sewer Work Prior to Paving (SM495170500):  Sewer work prior to paving.  (Nonassessable Sewer Maintenance Relay Fund -- $100,000).  The total estimated cost for this project including the requested amount is $1,500,000.  This project is anticipated to be completed during the 2017 construction season.

 

Various Aldermanic Districts:

 

E. Chicago St. - N. Jackson St. to N. Milwaukee St.; E. Chicago St. - N. Milwaukee St. to N. Water St.; N. Harbor Dr. - E. Polk St. to a point south of E. Chicago St.; S. Kinnickinnic Ave. - E. Lincoln Ave. to W. Lapham St.; N. Water St. - E. Kilbourn Ave. to N. Van Buren St. (ST216170104) File Number 161153:  High Impact asphalt surface overlay (Nonassessable High Impact Streets - $10,000).  The total estimated cost for this project including the requested amount is $1,200,000.  This project is anticipated to be completed during the 2017 construction season.

 

N. 12th St. - W. Center St. to W. Locust St.; N. Holton St. - W. Locust St. to W. Keefe Ave.; W. Locust St. - N. Sherman Blvd. to N. 51st St.; W. Vliet St. - N. 47th St. to N. 60th St.; W. Walnut St. - N. Dr. Martin Luther King Jr. Dr. to N. 6th St. (ST216170103) File Number 161153:  High Impact asphalt surface overlay (Nonassessable High Impact Streets - $10,000).  The total estimated cost for this project including the requested amount is $1,000,000.  This project is anticipated to be completed during the 2017 construction season.

 

N. 27th St. - W. Center St. to W. Townsend St.; W. Atkinson Av. - N. 27th St. to N. 32nd St.; W. Cameron Ave. - N. 32nd St. to N. 35th St.; W. Keefe Ave. - N. Sherman Blvd. to N. 51st St.; E. Kenwood Blvd. - N. Lake Dr. to N. Downer Ave.; N. Shepard  Ave. - E. Kenwood Blvd. to E. Hartford Ave.; W. Wells St. - N. 16th St. to N. 27th St. (ST216170107) File Number 161153:  High Impact asphalt surface overlay (Nonassessable High Impact Streets - $10,000). The total estimated cost for this project including the requested amount is $1,325,000. This project is anticipated to be completed during the 2017 construction season.

 

N. 60th St. - W. Vliet St. to W. Center St. (Portions in the City of Wauwatosa); N. 85th St. - a point south of W. Melvina St. to W. Melvina St.; N. 85th St. - W. Vienna Ave. to a point north of W. Vienna Av.; N. 94th St. - W. Center St. to point north of W. Center St.; N. 100th St. - W. Capitol Dr. to W. Grantosa Dr.; W. Bradley Rd. - N. 66th St. to N. 76th St. (portions in the Village of Brown Deer); W. Melvina St. - N. 83rd St. to N. 88th St. (ST216170106) File Number 161153:  High Impact asphalt surface overlay (Nonassessable High Impact Streets - $10,000). The total estimated cost for this project including the requested amount is $875,000. This project is anticipated to be completed during the 2017 construction season.

 

N. 68th St. - W. Villard Ave. to W. Silver Spring Dr.; N. 100th St. - W. Keefe Ave. to W. Lisbon Ave. (Portions in the City of Wauwatosa); W. Silver Spring Rd. - W. Silver Spring Dr. to N. Lover Lane Rd.; W. Villard Ave. - N. 68th St. to W. Grantosa Dr. (ST216170105) File Number 161153:  High Impact asphalt surface overlay (Nonassessable High Impact Streets - $10,000). The total estimated cost for this project including the requested amount is $675,000. This project is anticipated to be completed during the 2017 construction season.

 

S. 20th St. - W. Ramsey Ave. to W. Grange Ave.; S. Layton Blvd.- W. National Ave. to W. Evergreen Ln.; W. Lakefield Dr. - W. Morgan Ave. to S. 35th St.; W. Windlake Ave. - S. 7th St. to S. 16th St.  (ST216170102) File Number 161153:  High Impact asphalt surface overlay (Nonassessable High Impact Streets - $10,000).  The total estimated cost for this project including the requested amount is $1,100,000.  This project is anticipated to be completed during the 2017 construction season.

 

S. 27th St. (west roadway) - the railroad right of way south of W. Cleveland Ave. to W. Lincoln Ave.; E. Oklahoma Ave. - S. Superior St. to S. Kinnickinnic Ave. (ST216170108) File Number 161153:  High Impact asphalt surface overlay (Nonassessable High Impact Streets - $10,000). The total estimated cost for this project including the requested amount is $450,000. This project is anticipated to be completed during the 2017 construction season.

 

City of Greenfield

 

S. 108th St. - W. Beloit Rd. to W. Howard Ave. (WT410170003):  Hydrant and water main alterations.  (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $13,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2017 construction season.

 

;and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/Denise Reinholtz

Npr 6

12/28/2016