powered help
header-left header-center header-right
File #: 140122    Version: 0
Type: Resolution Status: Passed
File created: 5/13/2014 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 6/3/2014
Effective date:    
Title: Resolution relative to the cost participation and installation of temporary and permanent street lighting facilities in conjunction with Phase 2 of Federal and State Aid construction of the Zoo Interchange Project in the 10th Aldermanic District at a total estimated cost of $468,005.50 with one hundred percent of the total cost funded by the Wisconsin Department of Transportation.
Sponsors: THE CHAIR
Indexes: STREET LIGHTING
Attachments: 1. Agreement, 2. Project Cost Analysis, 3. Signed Agreement, 4. Comptroller's Certification, 5. Hearing Notice List
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
6/3/20140 MAYOR SIGNED   Action details Meeting details Not available
6/3/20140 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Video Video
5/21/20140 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Individual appearing: Bob Bryson - Department of Public Works
Pass3:0 Action details Meeting details Video Video
5/19/20140 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
5/13/20140 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
140122
Version
ORIGINAL
Reference

Sponsor
THE CHAIR
Title
Resolution relative to the cost participation and installation of temporary and permanent street lighting facilities in conjunction with Phase 2 of Federal and State Aid construction of the Zoo Interchange Project in the 10th Aldermanic District at a total estimated cost of $468,005.50 with one hundred percent of the total cost funded by the Wisconsin Department of Transportation.
Analysis
This resolution authorizes the Commissioner of Public Works and Comptroller to enter into a funding agreement with the Wisconsin Department of Transportation for installation of temporary and permanent street lighting improvements in conjunction with Phase 2 Federal and State Aid construction as part of the Zoo Interchange Project in the 10th Aldermanic District. The total estimated cost of this project is $468,005.50, with one hundred percent of the total cost funded by the Wisconsin Department of Transportation. This Resolution authorizes the Commissioner of Public Works to install these improvements upon execution of the agreement. This resolution also authorizes the Comptroller to establish and transfer funds to the appropriate accounts for the project.
Body
Whereas, The Wisconsin Department of Transportation will be reconstructing the Zoo Interchange at IH 94, IH 894, and USH 45; and

Whereas, Preliminary engineering work by City of Milwaukee street lighting, traffic signals, and traffic signs staff was authorized under Common Council File Number 111184; and

Whereas, The Zoo Interchange project provides cost participation for work by the City of Milwaukee for street lighting improvements in conjunction with construction that impacts street lighting facilities under the jurisdiction of the City of Milwaukee; and

Whereas, Phase 2 construction for the Zoo Interchange reconstruction project will include the reconfiguration of West Bluemound Road from North 94th Street to North 97th Street; North 9...

Click here for full text