File #: 091546    Version:
Type: Resolution Status: Passed
File created: 3/24/2010 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 4/13/2010
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $3,048,200 for a total estimated cost of $3,649,500.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Cover Letter, 2. Official Notice Number 73 committee actions, 3. Official Notice Number 73, 4. Sub. 2 Fiscal note, 5. Fiscal Note, 6. Hearing Notice List
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
4/29/20102 CITY CLERK PUBLISHED   Action details Meeting details Not available
4/22/20102 MAYOR SIGNED   Action details Meeting details Not available
4/13/20102 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
4/13/20102 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
4/13/20101 COMMON COUNCIL AMENDED

Minutes note: Ald. Hamilton moved to amend by adding the following: 1st Aldermanic District W. Lawn Ave. - N. 13th St. to N. Green Bay Ave. (ST211090114) File Number) 091545: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where needed, sodding (3.5-foot width of tree border area), grading, tree removal where necessary, and install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $52,800; Nonassessable Reconstruction Paving Fund -- $250,000). The total estimated cost for this project including the requested amount is $378,000. This project is anticipated to be completed during the 2010 construction season. This amendment would also increase the total estimated dollar amounts in the title from $2,745,400 to $3,048,200 and from $3,271,500 to $3,649,500.
Pass15:0 Action details Meeting details Not available
4/1/20101 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
3/30/20101 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass5:0 Action details Meeting details Not available
3/30/20100 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Individual present: Mary Dziewiontkowski, Dept. of Public Works
Pass5:0 Action details Meeting details Not available
3/26/20100 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
3/26/20100 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
3/26/20100 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
3/24/20100 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
091546
Version
SUBSTITUTE 2
Reference
091545
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $3,048,200 for a total estimated cost of $3,649,500.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $3,048,200. The total estimated cost of these projects is $3,649,500.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

1st Aldermanic District

W. Lawn Ave. - N. 13th St. to N. Green Bay Ave. (ST211090114) File Number 091545: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where needed, sodding (3.5-foot width of tree border area), grading, tree removal where necessary, and install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $52,800; Nonassessable Reconstruction Paving Fund -- $250,000). The total estimated cost for this project including the requested amount is $378,000. This project is anticipated to be completed during the 2010 construction season.

9th Aldermanic District

W. Brown Deer Rd. - N. 91st St. to N. 124th St. (State Highway 100) (ST320071001) (2150-05-70) File Number 090048: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where needed, including installation of new walk, sodding, adjus...

Click here for full text