File #: 111363    Version: 0
Type: Resolution Status: Passed
File created: 2/7/2012 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 2/28/2012
Effective date:    
Title: Resolution directing the Commissioner of Public Works to execute documents titled “State/Municipal Agreement for a Connecting Highway Improvement Project” with the Wisconsin Department of Transportation for the programming and construction of East Wells Street (USH 18) from North 6th Street to North Prospect Avenue at an estimated total cost of $7,228,000 at a 93 percent State and Federal share of which the preliminary engineering cost is $828,000, with the city's share being $207,000 and the grantor's share being $621,000 and West Highland Avenue (USH 18) from North 27th Street to North 12th Street at an estimated total cost of $4,390,000 at a 93 percent State and Federal share of which preliminary engineering cost is $300,000 with the city's share being $75,000 and the grantor's share being $225,000.
Sponsors: THE CHAIR
Indexes: AGREEMENTS, HIGHWAYS, STREET IMPROVEMENTS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Executed Agreements, 2. Agreement- 12th Street to 27th Street, 3. Agreement- 6th Street to Prospect Avenue, 4. Comptroller Certificate, 5. Hearing Notice List
Number
111363
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution directing the Commissioner of Public Works to execute documents titled “State/Municipal Agreement for a Connecting Highway Improvement Project” with the Wisconsin Department of Transportation for the programming and construction of East Wells Street (USH 18) from North 6th Street to North Prospect Avenue at an estimated total cost of $7,228,000 at a 93 percent State and Federal share of which the preliminary engineering cost is $828,000, with the city's share being $207,000 and the grantor's share being $621,000 and West Highland Avenue (USH 18) from North 27th Street to North 12th Street at an estimated total cost of $4,390,000 at a 93 percent State and Federal share of which preliminary engineering cost is $300,000 with the city's share being $75,000 and the grantor's share being $225,000.
Analysis
This resolution authorizes the Commissioner of Public Works to execute project agreements with the Wisconsin Department of Transportation (WisDOT) for the programming and construction of two (2) connecting highway projects with Federal/State Aid. These projects are included in the WisDOT’s current Connecting Highway program for improvement. The City is responsible for 25 percent of the preliminary engineering costs on these projects in accordance with WisDOT policy. City costs for the construction of these projects is dependent upon parking allowed. The estimated total cost of these projects is $11,618,000, of which the city’s share is $774,800. The total estimated preliminary engineering cost of these projects is $1,128,000, of which the City’s share is $282,000. This resolution also directs the City Comptroller to transfer funds for preliminary engineering for these projects.
Body
Whereas, Preliminary approval has been received from the Wisconsin Department of Transportation (WisDOT) along with agreements to be executed by the City of Milwaukee for the programming and con...

Click here for full text