powered help
header-left header-center header-right
File #: 080843    Version: 0
Type: Resolution Status: Passed
File created: 10/7/2008 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 10/29/2008
Effective date:    
Title: Resolution authorizing the Commissioner of Public Works to execute a Revised Project Agreement titled "State/Municipal Agreement for a Highway Improvement Project" between the City of Milwaukee and Wisconsin Department of Transportation associated with the bridge rehabilitation of the North Teutonia Avenue Bridge over West Silver Spring Drive with 80 percent Federal and/or State aid under the Local Bridge Replacement Program.
Sponsors: THE CHAIR
Indexes: AGREEMENTS, BRIDGES, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Cover Letter, 2. Fiscal Note, 3. Agreement, 4. Hearing notice list
Number
080843
Version
ORIGINAL
Reference
041494
Sponsor
THE CHAIR
Title
Resolution authorizing the Commissioner of Public Works to execute a Revised Project Agreement titled "State/Municipal Agreement for a Highway Improvement Project" between the City of Milwaukee and Wisconsin Department of Transportation associated with the bridge rehabilitation of the North Teutonia Avenue Bridge over West Silver Spring Drive with 80 percent Federal and/or State aid under the Local Bridge Replacement Program.
Analysis
This resolution authorizes the Commissioner of Public Works to execute a Revised Project Agreement with the Wisconsin Department of Transportation (WISDOT) associated with the bridge rehabilitation of the North Teutonia Avenue Bridge over West Silver Spring Drive. The Revised Project Agreement provides for 80 percent Federal/State aid and 20 percent local cost sharing for construction costs for the project. The total estimated construction costs for the project are $1,500,000 of which $300,000 is the City of Milwaukee’s share and $1,200,000 is the grantor share.
Body
Whereas, The Common Council of the City of Milwaukee adopted Resolution File Number 071479 authorizing and directing the Commissioner of Public Works to execute an agreement with the Wisconsin Department of Transportation (WISDOT) for bridge rehabilitation of the North Teutonia Avenue Bridge over West Silver Spring Drive with 80 percent Federal and/or State aid under the Local Bridge Replacement Program; and

Whereas, The construction costs for the bridge rehabilitation were within estimate but the accompanying Hazard Elimination Safety (HES) improvement to the interchange was under funded; and

Whereas, The HES project federal funding was capped resulting in construction costs in excess of this amount to be the responsibility of the City of Milwaukee; and

Whereas, The WISDOT has agreed the eligible HES construction costs could be included under the Local Bridge Replacement Progra...