Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $53,000 for a total estimated cost of these projects being $825,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Infrastructure Services Division Cover Letter, 2. Hearing notice list, 3. Fiscal note
Number
080387
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $53,000 for a total estimated cost of these projects being $825,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $53,000 with the total cost estimated to be $825,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

1st Aldermanic District

W. Reichert Pl. - N. 27th St. to 215 feet m/l West of N. 27th St. (SM495080054). Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000). The total estimated cost for this project including the requested amount is $33,000. This project is anticipated to be completed during the 2009 construction season.

3rd Aldermanic District

E. Boylston St. - N. Warren Ave. to N. Cambridge Ave. (SM495070098). Relaying combined sewer. The total estimated cost for this project is $53,000. This project is anticipated to be completed during the 2008 construction season.

N. Murray Ave. - E. Newberry Blvd. to E. Locust St. (SM495080055). Combined sewer lining. The total estimated cost for this project is $100,000. This project is anticipated to be completed during the 2008 construction season.

8th Aldermanic District

S. Layton Bd. - A Point south of W. National Ave. to W. National Ave. (ST211090127) Median revision. (Nonassessable Reconstruction Paving Fund -- $8,000). The total estimated cost for this project including the requested amo...

Click here for full text